— of — cables in scope are pulled (—% by count, —% by metres), — terminated. Last pulling recorded on —.
Cables that have reached each stage or beyond. A stage is read from the latest execution date on the cable (RI, IFC, Pulled, Terminated, Tested).
Cumulative design metres pulled per day against the straight-line plan from each team's plan start to its required finish date (Targets section below).
Weeks run Sunday to Saturday. Pulling counts cables with a pulled date in the week; termination counts cables with a connected date in the week. Targets are the weekly rates implied by the required finish dates; variance is actual minus target.
| Team | Target m | Pulled m | Var. m | % of target | Target cables | Pulled cables | Var. | Term. target | Terminated |
|---|
The saved finish dates per team are in targets.csv in the repository. Typing a date above recalculates everything on this page for you only; to change the plan for everyone, edit that file. Weekly target = work remaining at the plan start ÷ weeks to the finish. "Required now" = what is still left ÷ weeks left from this week. "vs plan" = metres pulled to date minus what the straight-line plan expected by today.
| Team | To pull | To pull m | Pulling finish | Weeks left | Target m/wk | Target cables/wk | Required now m/wk | vs plan (m) | To terminate | Termination finish | Term. target/wk | Required now/wk |
|---|
Cables grouped by the building of the destination equipment.
Owner is the engineer who holds the cable in the cable list. "Not IFC" cables still need design or routing.
| Owner | Cables | IFC | Not IFC | Pulled | Terminated |
|---|
Showing — of — matching cables (first 150 by tag). Narrow the filters or search to see the rest.
| Tag | Team | Unit | Type / size | From | To | Dest. bldg | Route | Design m | Pulled m | Status | Stage | IFC | Pulled | Terminated | Owner |
|---|
Del (deleted). Metres are design lengths from the cable list; "cut from drums" is the actual pulled length.